Table of Contents Table of Contents
Previous Page  44 / 390 Next Page
Information
Show Menu
Previous Page 44 / 390 Next Page
Page Background

Figure 4:

Pictures of 50FeSi furnace in Elkem Bjølvefosen with marked excavation front.

Wacker Chemicals. In August 2015, 33MW Si-furnace no 4 was shut down due to total

renovation project. Excavation started one day after the furnace was stopped. Furnace was

about 4m high and about 8.5m in inner diameter. Electrodes were cut before the excavation

began. In April 2016 a 13 MW Si-furnace no. 1 was also shut down. Furnace was about 3 m

high and about 5 m in inner diameter. Furnace was stopped with the electrodes down in

operating position. Excavation started one week after the production was ended. Despite of

small size of the furnace and relatively long period between shut down and excavation,

interior of the reactor was very hot.

Figure 5:

Pictures of furnace no.4 in Wacker with marked excavation front.

36