Table of Contents Table of Contents
Previous Page  42 / 390 Next Page
Information
Show Menu
Previous Page 42 / 390 Next Page
Page Background

In the lower part of the furnace the electrical energy is provided through an arc. Here the Si

producing reaction are taking place, (1) as well as the SiO(g) forming reactions (2) and (3):

SiO(g) + SiC = 2Si + CO(g)

(1)

2SiO

2

+ SiC = 3SiO(g) + CO(g)

(2)

Si + SiO

2

= 2SiO(g)

(3)

In the cavity, there will hence be a mixture of SiO and CO gas in addition to other high

temperature gas species. The cavity is formed due to the condensate (Si, SiO

2

, SiC) sticking

the charge together, creating a void below as the raw materials are consumed. As the SiO

2

starts to melt, in the condensate and in the raw materials, the mechanical strength of the roof

top will decrease, and hence the roof top temperature is in the area of 1650-1800 ºC [2]. The

arc is not necessarily a single arc. It can be multiple arcs as well. The arc will mainly go

towards the Si bath or the SiC crust and as calculated, the arc could be maximum 10-15cm,

based on the electrical parameters. It hence shows that

Error! Reference source not found.

is an illustration, and not showing the accurate scale.

As the gas species are ascending into the charge at lower temperatures, the major part of SiO

gas will react. The gas can react on the surface of the raw materials according to reversing

reaction (2) and (3), producing a condensate of SiO

2

, Si and/or SiC, or with the carbon added

according to reaction (4).

SiO(g) + 2C = SiC + CO(g)

(4)

The back reaction of (2) and (3) and reaction (4) will of course be very important regarding

obtaining a high Si yield and low energy consumption. For FeSi process the reduction of iron

oxides to metallic iron takes place in the upper zone of furnace.

By the term “metallurgical excavation” it is hence defined as: using personal only dealing

with the metallurgy in the furnace, taking and analysing samples and reporting their findings.

Generally, the metallurgical excavations of industrial furnaces are commonly carried out in

addition to the rapid reconstruction of furnaces (Si furnace in Elkem Thamshavn, FeSi

furnace in Elkem Bjølvefossen, Wecker Si-furnace no.4). This meant that the excavation and

sampling was also done as fast as possible. Hence, the geometry of the zones in the furnace

was based on visual estimation from the outside of the furnace and samples were picked as

they were removed from the furnace. There are a number of actions that is traditionally taken

during shut down in the belief that it will ease the mechanical excavation-especially when fast

re-building is the priority. One is to move the electrodes in the manner of “pushing” the metal

and slag out as well as freeing the electrodes. Another is to melt the charge down before shut-

down, meaning stopping the charging some time before shutdown in the belief that less

material will be easier to remove. As excavations of industrial and pilot scale furnaces are

quite seldom and in addition have a high cost, there is not a multitude of reported information.

Though there have been some reports from industrial excavations, the descriptions of zones in

the furnace have not been focused to big extend. However, publication by Tranell et al. [2]

reported the various zones in a FeSi furnace and the summary of this work is used in this

paper. Tangstad et al. also distinguished and described several zones in Si furnace after the

excavation in Elkem Thamshavn [3]. Recent three metallurgical furnace excavations give the

possibility to compare obtained data with the data published previously. The geometry of the

zones in a Si furnace is dependent on the operation history, and hence it can be a number of

different geometries, sizes and composition of the various parts of the furnace.

The Furnaces, furnaces operation and shot-downs.

Finnfjord furnace no. 1 produced FeSi75 alloy was operated at 17.5 MW. The furnace is

about 5 m in inner diameter and 2.5m high and it was stopped with normal operation with the

electrodes down in operating position due to scheduled maintenance. After the furnace was

stopped the charge materials at the top were stoked to get even surface. The surface in the

34