core

Process

during the prefabrication week, we cut all of the

angles of the mains columns at the workshop. We

also precut all of the elements for the cladding

since they need to be accurate with the angles of

the core.

on the site, the core has been the first element to

be set on the concrete slab. We used a template

at the bottom and at the top (perfectly pre-cut

with the lazercutter) to get the anlges. this two

elements were also used to brace the core during

the first day. then we add a bracing to connect it to

the main sutructure for the next days.

the cladding started later (after the platforms

were set) and was fitting very well. It was a

challenge because of all of the different angles

coming together. finally we put the roof made of

steel (as for the main structure).