Table of Contents Table of Contents
Previous Page  122 / 172 Next Page
Information
Show Menu
Previous Page 122 / 172 Next Page
Page Background

118

foundatIon

While making the plans for the foundations we

realised that we had to understand the actual

building process and therefore every step needed

specific information that should be explained co-

herently in different drawings.

first of all, we needed to make a big hole, so the

deepest heights should be referenced with the

structure in the ‘structure and lower slab plan’.

afterwards, the lower topography was refilled,

taking the measurements from the ‘digging plan’.

next, the insulation should be placed in the bot-

tom, and there they used the ‘Insulation and hole

plan’ to fill up the gaps underneath the concrete.

once they had the appropiate framework, they

needed the ‘reinforcement plan’ so that they could

place all the metal bars and create the beams un-

derneath the main and core structure.

the reinforcement bars had to be at least 100 mm

from the pilars in order to be able to screw the

bolts into the concrete without colliding with them.

they also had to have a different diameter accord-

ing to where they were placed.

When getting to the site we found out that there

had been little mistakes during the building pro-

cess, which taught us how important it is to keep

communication with the builders. the slope had

no inclination for the rain, the ring beam in the

concrete was too narrow and the shape of the core

was slightly deformed in one of the sides. however,

these small issues were not enough to stop us, and

we kept on building.

foundatIons on sIte

foundatIons WIth BuIldIng fInIshed

A

300

300

70

120

150 5

10

10

40

draining system

terrain gravel

reinforced concrete slab

rock wool insulation

1500

750 260 280

100 695

600

280 260 750

570

770

250

400

600

430

16 16

40 30

30

200

280 440

1250

2075

1860

1250

fire ventilation

2% fall

0

0.5 1m

1470

600

3485

1645

865

1645

2750

1285

3190

1035

3530

2615

2500

1150

935

600

975

910

600

250

400

250

1580

750

1105

starting of rain gradient

pipe

insulation

1

2

3

C

B

A

C

B

A

A

215

2500

2500

215

965

5430

5430