This is where all of our weekly progress will be recorded

Monday 19/02.24

Today we finished measuring the x and y axes and cut them, along with their lead screws. They all fit nicely in the freezer.

We started by very precisely measuring the cutting-line. Then we brought the profiles and screws down to the workshop and got them cut.


The new profiles were prepared by filing down sharp edges and threading new M5x0.8 holes.


Finally the CNC axes were assembled by following the instructions.


Insert Images


Tomorrow we will finish the installation of the CNC while simultaneously thinking of how to install a stable z-axis and a well functioning clamping method. 


Tuesday 20/02.24



Wednesday 21/02.24



Thursday 22/02.24



Friday 23/02.24