1. Get proof of successful prostate drilling
WHY: This will strengthen the validity of both the masters and the hardware X.
TIME: We estimate this will take 2 weeks, being completed by 26. Jan.
ALTERNATIVE: The alternative to this is keeping the current tissue results.
2. Create new iteration of prototype
WHY: A working product is to be delivered to the MR Core Lab.
TIME: We estimate we will have approximately 3 months available for this task.
ALTERNATIVE: No.
3. Write Hardware X article about the final prototype
WHY: This will make it easier for sensors to argument that our masters thesis is "publishable" which will act in our favor on the grade
TIME: We estimate we will have approximately 2 weeks available for this task.
ALTERNATIVE: Don't spend time doing this.
4. Write Master Thesis
WHY: Because its fun.
TIME: We estimate we will need 1 Month minimum. Deadline is 10. June, so the writing has to begin for full 10. May.
ALTERNATIVE: Work at Ohma Electra selling hot dogs.