Phase 4

BuIldIng Process

after all the detailing and drawings were completed, we were ready to

build the star cube. this phase consisted of 2 weeks. the first week

was spent in the workshop at ntnu prefabricating as many elements

as possible so that they just needed to be assembled on site in rindal.

one group was at havdal farm outside trondheim working on the

shingle facade.

after a long and hard week, it was time to transport everything to

rindal and begin assembling the structure. the photos of the process

follow.