Date
Attendees
- Jan Otto Reberg
- Gara Quintana
- Unknown User (joaoff)
- Unknown User (julianve)
- Unknown User (sivertba)
- Kanna Rajan
- Tor Arne Johansen
Goals
- Concept document sent out
- GOMSpace notes sent out
- Gantt Chart (new)
- ESA workshop application
- Presentations on 23. and 24. Nov
Discussion items
Time | Item | Who | Notes |
---|---|---|---|
Action items
Data from HSI
Hardware
- Distances between lenses fixed?
Software
- Test on the projection core
- Comms. for memory
- Test this on the test development board soon
- Bitwidth for loadings and data established?
Mission Design
- Determining constraints for data processing for a target of 50x30 km (provides requirements for Idletechs processing
- Possible to do the OTFP during the exposure times? Likely better to collect all data then do the processing (another limit on time schedule) - need to see if it can be done less than a minute.
- Have 1 minute spare to do processing and then downlink in 1 min
- Precision of imaging