Created by Unknown User (sivertba), last modified on 05.09.2018
Date
Attendees
Goals
- Clarify problems with the current version of Pipline flowchart
- Clarify mission requirements impacts for HSI payload
- Clarify the status of FPGA etc.
Meeting Notes
- The flowchart has been transferred to draw.io
- The flowchart has been separated into three different subsystems i.e. satellite communication, onboard processing, and ground segment
- Some lines are confusing as they should not be uploaded just to be downloaded again
- Some confusion regarding definitions of levels, Mariusz will talk with Gene Carl Feldman to clarify regarding what Level 1A entails
- some blocks in the processing chain do not make, i.e. the spectral correction is not an image processing action
- Another meeting will take place in 1 day, to discuss furthere