Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  • Shutdown and remove all servers from all eight racks. Leave the switches and cabling. Move the racks, so the carpenters can rebuild the floor.
  • Build support framing for the legs that supports the floor tiles. Replace the floor tiles with thicker tiles.
  • Put all servers back in the racks, and make sure everything still works as normal.

Event log

TimeEvent
15
16.12.23 - 20:22The broken floor tile was discovered
15
16.12.23 - ca. 23:00Agreed that we should remove some weight from R3, and contact help on Monday
15
18.12.23 - ca. 09:00Contacted a company that will assess the damage, and come up with a plan to fix the floor
18.12.23 - ca. 12:00

Placed a steel beam under R3, to support it.

Migrated all VMs from five of the compute nodes in R3, and removed them from the rack

20.12.23Visit from the carpenter company. Made an initial plan for what needed to be done. Decided that the steel beam would suffice for support. Little to no measured further "sinking".
17.01.24 - 10:00

Meeting with the carpenter. A plan was made for repairing the floor. They will build support framing between all the floor tile legs, and replace all necessary tiles.

The carpenters will need two days, and we schedule two days for removing all servers, and one day to put everything back in after the floor is fixed. Meaning a total downtime of five days.

18.01.24 - 13:00Received confirmation from the carpenter, that they can start the repair work on 6th of February. We accepted the offer.