Comment: Task marked complete

Date

Attendees

Action items

•Status on project:
–Hopavågen testing: no updates
–Workshop May 4th: what should be the agenda?
•Please think of something before next meeting
•Processing – how to proceed + what we have
•What is needed
•Testing possibilities in the US
–Funshop before summer: teamwork and project planning
•Should be in May (first 16/5, then none, then June)
–Julian needs more people to work on the prototype
–Camera driver: Joao and Dennis will interface on requirements.
–EMECS room: there is a room on the 3rd floor staircase
–SmallSat lab: flooring is being put down
•Status per team
–Systems engineering: “Vibration testing expert” Viggo Pedersen @ NTNU met last week, scheduling follow-up in 1-2 weeks.
–Flight tests: May and June are pretty open, since weather is getting good it might be filling up (the pilots’ availabilities)
•Update on action items
–Optical analysis
1.Perform structural analysis and determine worst-case distortions
2.Use worst-case in optical model and perform Monte Carlo or similar analysis to see optical performance
3.Take that information back to mechanical design + analysis
4. Improve mechanical design, iterate