This page describes the S-TEAM milestones as set out in the technical annex ([STAN84|steam:Useful documents^STAN84.pdf]).

...

  Milestones

...

Milestone

...

Description

...

Due

...

 

...

Status

...

MS1

...

Website, digital depository, startup meeting

...

M1

...

 

...

completed

...

MS2

...

Completion of national workshops programme

...

M6

...

End of financial reporting period 1

...

in progress

...

MS2a

...

International workshop and report

...

M9

...

 

...

in progress

...

MS3

...

MB3, provisionally during ASE 2010 in Nottingham

...

M9

...

Decision req'd on ECIP launch conference

...

in progress

...

MS3a

...

Paper presented to ASE2010

...

M9

...

 

...

 

...

MS4

...

MB4

...

M12

...

Production of non-mandatory annual report

...

 

...

MS5

...

MB5

...

M15

...

Internal pre-review and external evaluators' report in preparation for technical review

...

 

...

MS5a

...

ECER 2010

...

 

...

Combined with MB5?

...

 

...

MS6

...

MB6

...

M18

...

EC Technical review and mid-project report

...

 

...

MS6a

...

 

...

M18

...

International conference

...

 

...

MS7

...

MB7

...

M21

...

Consideration of project review

...

 

...

MS8

...

MB8, Completion of M24 deliverables

...

M24

...

production of second annual report

...

 

...

MS9

...

MB9

...

M30

...

Consideration of external evaluators' final report (may be deferred to M33)

...

 

...

MS10

...

MB10

...

M33

...

End of project conference

...

 

...

MS11

...

MB11

...

M36

...

Final meeting and mandatory reports

...

 

...

 

...

 

...

 

...

 

...

 are points  where we stop  and think about where we are and what has to be done next. Click on a milestone below for a report (if milestone completed) or more infomation (if milestone lies ahead).

|| Milestone \\ || Description || Due || || Status ||
| [MS1|^S-TEAMMilestone1.pdf] | Website, digital depository, startup meeting \\ | M1 | | completed |
| MS2 | Completion of [national workshops|national workshops and liaison partners] programme \\ | M6 | End of financial reporting period 1\\ | in progress \\ |
| MS2a | International workshop and report \\ | M9 | | in progress \\ |
| MS3 | MB3, provisionally during [ASE 2010|http://www.ase.org.uk/htm/conferences/annual_conference_2010/index.php] in Nottingham \\ | M9 | Decision req'd on ECIP launch conference\\ | in progress \\ |
| MS3a | Paper presented to ASE2010\\ | M9 | | |
| MS4 | MB4 | M12 | Production of non-mandatory annual report\\ | |
| MS5 | MB5 | M15 | Internal pre-review and external evaluators' report in preparation for technical review\\ | |
| MS5a | ECER 2010\\ | | Combined with MB5?\\ | |
| MS6 | MB6 | M18 | EC Technical review and mid-project report\\ | |
| MS6a | | M18 | International conference\\ | |
| MS7 | MB7 | M21 | Consideration of project review\\ | |
| MS8\\ | MB8, Completion of M24 deliverables | M24\\ | production of second annual report\\ | |
| MS9\\ | MB9\\ | M30\\ | Consideration of external evaluators' final report (may be deferred to M33)\\ | |
| MS10\\ | MB10\\ | M33\\ | End of project conference\\ | |
| MS11\\ | MB11\\ | M36\\ | Final meeting and mandatory reports\\ | |
| | | | | |