Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Question on what kind of partnership we want. --> We want an active partner, more than a pure supplier. 
Notes from presentation of UTIAS: 
  • Self-funded, not-for-profit. All funding from contracts. 35 engineers, 15 grad students. 
  • Have 18 sats operational. 15 awaiting launch.
  • Can vere open for

...

  • exchange/research stays.

...

  • Must be, to some extent, clarified and organized by the university itself.

...

  • Must clarify opportunities. 
  • Smallsats are a design approach, not a size. 
  • Not doing a lot of CubeSats, but are open for it, esp. if its a longer series of satellites. 
  • Integration of spacecraft on-site (NTNU) can be

...

  • feasible
  • Launch: Have supported a wide range. (Must get a up-

...

  • coming manifest). 
  • Typical orbits are 500-650 km, 09:30 - 10:30

...

  • ascending/

...

  • descending node. 
Does not see any immediate pit-falls. Constraints/requirements
  • Sleep-power: Will be higher than "expected", need to keep a reasonable amount of minimum operations in order to ensure good operation and wake-up. 3 -  4 W. 

...

  • ADCS: 
    • Must look into this exp. on 3U. On bigger buses this is less of an problem. 
    • Pointing

...

    • knowledge with star-tracker is very good. 
    • Pointing accuracy

...

    • it more challenging, but should be better than 0.5 deg if good calibration. 
    • During slew, should be at 0.2-0.1 during

...

    • maneuvers. 
    • The type of reaction wheels must be looked into for 3 U. A bit more of a challenge. 
    • Limb-to-limb pointing might be a issue

...

    • , as to find where the star-tracker can point. 
    • Must avoid sun into the sensor

...

    • . 
    • Higher latitudes should be fine, but further south might be more of an issue. 
    • Can be a bit of a time-variance wrt. position of sun/moon/earth-interactions. 
    • Have GPS, better than 10 meters. 
  • Communications:
    • S-band down, UHF up. 
    • Active pointing of the antenna. 2 Mbps (with pointing). 
    • Standard, nominal, mode is more like 128 kbps --> works for all attitudes. 
    • Uplink is typically 4 kbps. Have always supported re-programming. 
    • Spend a day to upload the file, then do verification and load. 

...

  • Integration/test
    • Operational software are available. Encourage testing using operational software during

...

    • tests on ground. FFI and Statsat have this. 
    • Training: Can happen at UITAS, or NTNU. 
    • Have a flat-sat, made up by spares. Could then be used as spares for the flight model if needed. Does not really make an EM of flight heritage components. Go right to proto-flight if its only small changes. Does not expect any new equipment, but will probably have some suggestions on how to build the payload. 
    • On-board interfaces:

...

    • Communication limited to 1 Mbps or 500 kbps. CAN or serial of some sort. Should have around 1 GB storage on the onboard-processing. Also used as buffer before transmit. Have a NSP (nanosat communication protocol). 
    • OS: Cano. In-house system. Not really open for us. ADCS is probably not really

...

    • accessible; perhaps with permission. Could provide some interface of to software that we could run. 
    • Interaction between payload and OBC:

...

    • Should be limited to data exchange. Commanding should go through mission planning software (GS). Upload target, time, when. Time-tagged commands. Not any feedback on what going on. Onboard autonomy means different things.... Using a hand-full of high-level commands. Like "point here", take image. The detailed maneuver will be solved in the space craft. 

 

  • Could be able to operate on input from the payload, but perhaps go through the GS first. 
  • Does not currently have SDR. 

...

  • Export: Formally, will need an export agreement, should not be a problem. Need to look into which students can be in the project and so on. 

 

Next steps: 
UTIAS: Inform Rob, internal discussion. Size of spacecraft, sharing agreements and so oon. Ask for more info when required
Need some more requirements NTNU: Prepare list of initial reqs in order to get a ROM.